Background
A Stable and Predictable Federal Gas Tax Fund
Canada’s Gas Tax Fund transfers $746 million to Ontario municipalities each year for environmentally sustainable infrastructure. Since the launch of the fund in 2005, Ontario municipalities have invested more than $2.1 billion of funding into more than 3,800 infrastructure projects worth over $6.7 billion.
Originally launched as a five-year program, Canada’s Gas Tax Fund has now been made permanent through federal legislation. Municipalities in Ontario can rely on the Government of Canada as an essential long-term partner in the building of our communities.
2011
PERTH Road 119 RECYCLING AND RESURFACING INCLUDING MINOR IMPROVEMENTS OF CURBS AND DRAINAGE
Location:
Perth Road 119 from Stratford to Milverton Total Length: 23.7 KM
Description:
Cold in Place recycled and overlaid with hot mix that includes RAP which will reduce the identified capital needs of the County and improve the quality of the road leading to improved safety and reduction of greenhouse gases. The asset lifespan of this road section will be extended to 15-20 years.
Total Cost of the Project: $4,047,644
Gas Tax Funding: $1,210,322
Installation Solar Panel at Mitchell work yards
Location:
52 Frank Street, Mitchell, ON.
Description:
Perth County installed solar arrays of 10 kW, which feed the energy produced into the hydro grid under the current Provincial feed in tariff (FIT) program. This array will produce 15,655 kWh per year, reducing the County’s GHG emissions by 10.6 tons of CO2. This will resulted in less operating cost and CO2 reduction.
Total Cost of the Project: $103,223
Gas Tax Funding: $103,223
2010
Replacement of Culvert
Location:
Perth Road 147, Lot 31 -32, Conc 7, Elma TWP.
Description:
Replacement of the culvert will renew this particular capital asset, with a predicted lifespan of 80 years. The project will use pre-cast concrete sections, significantly shortening the construction period, allowing traffic to travel unimpeded for longer than would otherwise be expected with this type of project.
Total Cost of the Project: $ 424,011.27
Gas Tax Funding: $ 424,011.27
Reconstruction of Perth Road 180 and Structure # 180145
Location:
Perth Road 180 and Structure #180145 in Dublin Ontario.
Description:
Extends the asset lifespan of this road section for 15-20 years, will incorporate significant quantities of recycled and reclaimed material, and will alleviate existing issues with drainage and flooding.
Rehabilitation of County Bridge #180145, greatly increasing the remaining life expectancy of this asset by 40-50 years, which decreases the County's long-term capital needs.
Total Cost of the Project: $ 698,923.53
Gas Tax Funding: $ 698,918.56
2009
Perth Line 32 Resurfacing
Location:
Perth Line 32, from Perth Road 130 to Perth Road 122
Total Length: 4.1 KM
Description:
Cold in Place recycled and overlaid with hot mix that includes RAP which will reduce the identified capital needs of the County and improve the quality of the road leading to improved safety and reduction of greenhouse gases. The asset lifespan of this road section will be extended to 15-20 years.
Total Cost of the Project: $521,365.54
Gas Tax Funding: $473,365.54
Perth Road 139 Resurfacing
Location:
Perth Road 139, from Perth Road 180 to Town of St. Mary's limit.
Total Length: 9.0 KM
Description:
Cold in Place recycled and overlaid with hot mix that includes RAP which will reduce the identified capital needs of the County and improve the quality of the road leading to improved safety and reduction of greenhouse gases. The asset lifespan of this road section will be extended to 15-20 years.
Total Cost of the Project: $1,300,245.09
Gas Tax Funding: $1,127,608.43
2007
Perth Road 163 Resurfacing
Location:
Commencing at Rannoch and extending north for 7.9 kilometres.
Description:
Cold in Place recycled and overlaid with hotmix that includes RAP which will reduce the identified capital needs of the County and improve the quality of the road leading to improved safety and reduction of green house gases. The asset lifespan of this road section will be extended to 15-20 years.
Total Job Cost: $992,000.00
Gas Tax Funding: $593,493.67
2006
Perth Road 135 Resurfacing
Location:
Commencing at the north limit of Rostock, north to Perth Line 55. Distance of 6.1 kilometres.
Description:
Cold in Place recycled and overlaid with hotmix that includes RAP which will reduce the identified capital needs of the County and improve the quality of road leading to improved safety and reduction of green house gases. The asset lifespan of this road section will be extended to 15-20 years.
Total Job Cost: $615,141.38
Gas Tax Funding: $579,790.70
Culvert Replacement 044-013
Location:
Concession 8, Lot 3 Township of Perth East, Ellice Ward
Description:
The culvert at this location was replaced resulting in a reduction of the identified capital costs needs of the County, safety improvements and elimination of the need for load limit restrictions.
Total Job Cost: $214,301.01
Gas Tax Funding: $ 33,733.00
Culvert Replacement 086-103
Location:
Concession 1, Part Lot 1 Township of Perth East, Mornington
Description:
The culvert at this location was replaced resulting in a reduction of the identified capital costs needs of the County, safety improvements and elimination of the need for load limit restrictions.
Total Job Cost: $129,429.99
Gas Tax Funding: $18,333.00